SWELL Construction

Project status:
Current

Project: City of Palmerston is redeveloping the Palmerston Swimming and Fitness Centre into a Swimming, Wellness, Events, Leisure and Lifestyle precinct for the entire community to enjoy.

Overview

The proposed SWELL (Swimming, Wellness, Events, Leisure, Lifestyle) master plan is part of Council’s strategic vision to provide Palmerston residents with a contemporary and family friendly, water and lifestyle precinct.

Located in Moulden, Palmerston, the ageing facility will be upgraded to cater to a wider range of interests to support Palmerston’s growing population. 

The redevelopment will include:

  • refurbishment of the 50-metre pool
  • a toddlers zero depth and play pool
  • an events area
  • basketball half court
  • new and improved accessible toilets and change rooms
  • aquatic play structure
  • energy efficient, modern pool plant and equipment and shade features.

 

Cost

The City of Palmerston, the Northern Territory Government and the Australian Government have committed $19.4M towards this project.

Construction Timeline

Early stages of construction are taking place now with works expected to be completed by November 2023.

The following are approximate timelines of the project and are updated as the project progresses. 

2022
Oct-Nov: Demolition
Nov-Feb: Underground works
2023
Feb: Half court basketball / BBQ area
Mar: Refurbishment of amenities and store rooms
May: Walkway structures
Jun: Zero-depth pool
Jun: Adventure Play structure
Aug: Program warm-water pool
Aug: Refurbishment of 50m swimming pool
Oct: Completion and inspection
Nov: Opening

Current Status
  • The Youth Centre and Gym have a new access point and will continue to operate as normal at this stage
  • Removal of redundant underground services
  • Removal of waste material from site
  • Improved signage at the facility
Looking Ahead
  • Improved signage at the facility
  • Manufacturing of shade structure
  • Upgrading existing amenities 
  • Installation of basketball court
Progress Photographs - as at January 2023





Progress Photographs - as at December 2022





Progress Photographs - as at October 2022



Progress Photographs - as at September 2022








Works will take place Monday to Saturday between the hours of 7am to 5pm. Where any local traffic diversions or night works are required, advance notice will be given to nearby residents and businesses.

The public swimming pool will be closed for the duration of construction, while the fitness centre will remain open. We thank you in advance for your patience and consideration.

More information 

If you require additional construction information or would like to discuss the project, please contact Council on 8935 9922.

Key Documentation

Factsheet
Newsletter Edition 1
Newsletter Edition 2